Total Bond Project costs: $1,029,100.00 |
|
Scope: Conversion of building to shared-use
facility: Infirmary and Campus Police & Security |
|
Current status:
Designer to begin construction documents after approval by
University |
|
Project Architect: J.N.Pease & Assoc.
Charlotte, North Carolina |
|
Construction scheduled to begin Winter 2001 |
|
|
|
|
|
|
Total Bond Project costs: $15,146,900.00 |
|
Scope: Additional stand alone building and
renovations to the existing Lyons Science Complex |
|
Current status: Designer is working with
University stakeholders to develop program |
|
Project architect: The Freelon Group, Research Triangle Park, North Carolina |
|
Construction Management Firm: Construction
Control Corporation, Inc.,
Columbia, South Carolina |
|
Construction scheduled to begin Fall 2003 |
|
|
|
|
|
|
Total Bond Project costs: $6,872,300.00 |
|
Scope:
Construction of new Residence Hall to relieve critical housing
shortage on campus. |
|
Current status: Site selection under review by
senior University
administration. Designer is
working with University stakeholders to develop program. |
|
Project Architect: SFL+A and The New Synergy, Inc. Fayetteville, NC/ Durham, NC |
|
Construction scheduled to begin Fall 2002 |
|
|
|
|
|
|
Total Project costs: |
|
Bond Funds: $6,325,000.00 |
|
Special App.:$ 500,000.00 |
|
Total: $6,825,000.00 |
|
Scope: Comprehensive renovations and addition |
|
Current status: Designer is working with
University stakeholders to develop program |
|
Project Architect: Pearce, Brinkley, Cease, + Lee, Inc. Raleigh, North Carolina |
|
Construction scheduled to begin Spring 2003 |
|
|
|
|
|
|
|
|
|
|
|
|
Total Bond Project costs: $1,740,500.00 |
|
Scope:
Comprehensive renovations including construction of elevator tower |
|
Status:
Designer selection process to begin Winter 2002. |
|
Construction scheduled to begin Fall 2003 |
|
|
|
|
|
|
Total Bond Project costs: $3,360,000.00 |
|
Scope:
Comprehensive renovation and change of use to academic facility |
|
Status:
Designer selection process to begin Winter 2002 |
|
Construction scheduled to begin Winter 2004 |
|
|
|
|
|
|
Total Bond Project costs: $3,256,400.00 |
|
Scope:
Comprehensive renovation and conversion of use to student services
facility |
|
Status:
Designer selection process to begin Winter 2003 |
|
Construction scheduled to begin Winter 2005 |
|
|
|
|
|
|
Total Bond Project Costs: $432,600.00 |
|
Scope:
Comprehensive renovations |
|
Status:
Designer selection process to begin Winter 2003 |
|
Construction scheduled to begin Fall 2004 |
|
|
|
|
|
|
Total Bond project cost: $884,300.00 |
|
Scope:
Comprehensive renovation |
|
Status:
Designer selection process to begin Winter 2004 |
|
Construction scheduled to begin Fall 2005 |
|
|
|
|
|
|
Total Bond Project costs: $875,900.00 |
|
Scope:
Comprehensive renovations and modernization |
|
Status:
Designer selection process to begin Winter 2005 |
|
Construction scheduled to begin Spring 2006 |
|
|
|
|
|
|
Total Bond Project costs: $640,600.00 |
|
Scope:
Comprehensive renovations |
|
Status:
Designer selection process to begin Winter 2005 |
|
Construction scheduled to begin Winter 2006 |
|
|
|
|
|
|
Total Bond Project costs: $1,773,500.00 |
|
Scope:
Comprehensive renovations and change of use to academic and student
service facility |
|
Status:
Designer selection process to begin Winter 2006 |
|
Construction scheduled to begin Winter 2007 |
|
|
|
|
|
|
|
|
Total Project budget: $1,920,925.13 |
|
Scope: New roadway to connect east and west
campus and to include sidewalks, lighting, landscaping, and other
amenities. |
|
Status: Contracts at State Construction under
negotiation |
|
Project Engineer: Moorman, Kizer, Reitzel,
Inc. Fayetteville, NC |
|
|
|
|
Projected costs: |
|
$1,200,000.00 - $1,500,000.00 |
|
Scope:
To construct grandstands for relocation of new home side and
expansion of both end zones. New total stadium capacity of 6,500-7,000
seats. New state-of-the-art press box,
football coaches offices, weight room facility, and public address system. |
|
Funding:
Funding source options are being reviewed and will be presented at
next Board of Trustees meeting. |
|
|
|
|
|
|
|
|
|